Immission control - Submit measurement report on individual measurements of air pollutants in medium-sized combustion plants in accordance with the 44th BImSchV

If you are the operator of a medium-sized combustion, gas turbine or internal combustion engine installation, you must, under certain conditions, have its pollutant emissions and exhaust gas loss checked by means of individual measurements.

You must have the measurements carried out by a notified body (measuring centre) in accordance with Section 29b of the Federal Immission Control Act. For certain combustion plants under 10 megawatts that do not require a licence, you can also have the measurement carried out by a chimney sweep (Section 31 (9) of the 44th BImSchV).

The measurement report or the chimney sweep's certificate of the measurement must be submitted to the authorities immediately.

Responsible authority

The responsibilities in the area of immission control are regulated in the Immission Control Competence Ordinance of the state of Baden-Württemberg.

In most cases, the competent authority for plants that fall under the 44th BImSchV is the local lower immission control authority, i.e

  • the district office if the premises with the plant are located in a district,
  • the city administration if the premises with the plant are located in a city district.

A different responsibility applies in the following cases (e.g. for companies that are subject to the European Industrial Emissions Directive, the Hazardous Incident Ordinance or mining law):

Departments 5, Environment of the respective locally responsible regional councils are the competent immission control authorities for company premises on which

  • at least one installation that is labelled with the letter E in column d of Annex 1 of the Ordinance on Installations Requiring a Permit,
  • at least one operating area in accordance with Section 3 (5a) of the Federal Immission Control Act (hazardous incident operation),
  • at least one installation that requires a licence pursuant to Section 60 (3) sentence 1 no. 2 or no. 3 of the Federal Water Act, or
  • at least one landfill in accordance with Article 10 in conjunction with Annex I of Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control), as amended

exists or is to be constructed.

Department 9, State Office for Geology, Raw Materials and Mining of the Freiburg Regional Council is also the state-wide competent immission control authority for

  • Operational sites, including the facilities and activities located on them, which are subject to mining supervision,
  • Operating sites with cable cars and funicular railways used for passenger transport,
  • Operating sites with high-pressure gas pipelines which, as energy installations within the meaning of the Energy Industry Act, serve to supply gas and which are designed for a maximum permissible operating pressure of more than 16 bar,
  • Underground waste disposal facilities and
  • Sites with installations used for the construction, significant expansion and significant modification of underground cavities.

Details

Prerequisite

  • You are the operator of a medium-sized combustion, gas turbine or internal combustion engine plant.
  • You have commissioned your plant or made emission-relevant changes.

Procedure

  • You contact a notified body (measuring centre) in accordance with Section 29b of the Federal Immission Control Act. For certain combustion plants under 10 megawatts that do not require a licence, you can also have the measurement carried out by a chimney sweep (Section 31 (9) of the 44th BImSchV).
  • The measuring centre or the chimney sweep will determine the emission values on the measurement date.
  • Once the measurements have been completed, you will receive a measurement report from the measuring centre or the chimney sweep, which must be submitted to the responsible immission control authority.

Deadlines

The measurements must be carried out within 4 months of commissioning the system or at the latest 4 months after an emission-relevant change. You must submit the measurement report or certificate to the competent authority without delay.

Required documents

Complete measurement report in accordance with Annex A of Guideline VDI 4220 Sheet 2 (November 2018 edition) with information on, among other things

  • Measurement results,
  • measurement methods used,
  • Operating conditions that are important for the assessment of the measurement results.

If the measurement was carried out by the chimney sweep:

  • Certificate from the chimney sweep about the measurement

Costs

None

Miscellaneous

Please ensure that you submit the measurement report to the immission control authority responsible for your plant.

Legal basis

Bundes-Immissionsschutzgesetz (BImSchG)

  • § 26 Messungen aus besonderem Anlass
  • § 28 Erstmalige und wiederkehrende Messungen bei genehmigungsbedürftigen Anlagen

Verordnung über mittelgroße Feuerungs-, Gasturbinen- und Verbrennungsmotoranlagen - 44. BImSchV

  • § 31 Einzelmessungen

Release note